http://fukushima-diary.com/2012/07/reactor4-one-fuel-assembly-was-taken-out-the-rest-for-tomorrow/
[Reactor4] One fuel assembly was taken out, the rest for tomorrow
Posted by Mochizuki on July 18th, 2012 · 1 Comment
Following up this article..[Reactor4] New assembly taken out on 7/18, IAEA might visit Fukushima plant
As the actual Fukushima worker Happy11311 commented, Tepco managed to take out one of the new fuel assemblies from SFP4 already.
At this moment, the taken assembly is not put in the cask yet.
The other one is to be taken out tomorrow 7/19/2012 (JST).
Today Japan meteorological agency announced thunderstorm advisory.
and news of the day from ENE News.....
Latest Headlines:
and...
[Reactor4] New assembly taken out on 7/18, IAEA might visit Fukushima plant
Posted by Mochizuki on July 17th, 2012 · 2 Comments
Following up this article..[Reactor4] Tepco will not announce when to take out the fuel from SFP4
Though Tepco was concealing the specific data to take out the new assemblies, TBS reported it will be 7/18/2012 (JST).
Actual Fukushima worker Happy11311 commented it may take up to 2 days.
<Translate>
Usually it takes 1 day to lift up 2 fuel assemblies, but they need to be extraordinarily careful this time, so it might take them 2 days. I guess they will start it on 7/19 if they take 1 day, will start it on 7/18 if they take 2 days.
<End>
<Translate>
7/20 may be the spare day in case of rain. and they will restart Ohi unit4 on 7/18 and 7/19. Even now, sometimes Japanese government double-book their plans in Fukushima plant with something else. I suspect it’s to distract mass media and people or not..
<End>